Gantt Calendars Project Configuration

Modified on Fri, 01 Dec 2023 at 05:32 PM

This is a new feature available from Nextedy Gantt version 23.9.0.
This feature allows you to set the Polarion project as Working Calendar.

In this documentation, we'll guide you through setting up a Polarion project structure for managing calendars and work items.
Follow these steps for a seamless setup.


Project Administration > Work Items > Enumerations

- Workitem Types:

You need to define the following work item types:
- Calendar;
- Time Off;
- Time On;
- Tweak;



- Link Roles:

Define the relationships between work items:

- Calendar can inherit/be inherited by another Calendar.
- Calendar can be affected by TimeOff, TimeOn, and Tweak.
- TimeOff, TimeOn, and Tweak can affect Calendar.




- Weekday Enum:

Create an enumeration of weekdays, including Monday to Friday, and an "All" option.




Project Administration > Work Items > Custom Fields

Ensure that you set up the required custom fields for each work item type. This is critical for the functionality of your project.

Configuration for custom fields:


- Calendar:


- Tweak:


- Time Off:


- Time On:




Setup Project to Use Work Item Calendar

To enable the "Work Item Calendar" functionality within your project, add the following lines to the Administration -> Configuration Properties of the project:
nextedy.gantt.workitemCalendar.projectId=<PROJECTID>

nextedy.gantt.workitemCalendar.globalID=<WORKITEMID>


- Replace <PROJECTID> with the projectId of the Calendar Project.

- Replace <WORKITEMID> with the work item ID of a calendar type work item that should be used as the global calendar. 

If you don't want to create a new one, you can use a placeholder empty calendar.


NOTE! Specify the following configuration properties in both target and source projects.



By following these steps and configurations, you'll have a well-structured Polarion project ready to manage calendars and work items efficiently.


In the following article, we will focus on the functionality that this feature brings.


Check also:

- Gantt Calendars main functionality info: click here

- Gantt Chart for Calendars setup: click here



In case of questions please contact support@nextedy.com


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons

Feedback sent

We appreciate your effort and will try to fix the article