Sometimes you want to show the project plan in the timeline, but in the resource load table bellow the timeline the system should count items from other projects as well.
You can achieve this by:
- query items from multiple projects
- and filtering out item on the timeline pane of the gantt. To filter the items out from the timeline pane, you need to use item script:
(in this example we filter out every item from project different to "gantt2"