How to set the Gantt time range?
By default the Gantt chart shows the time range as small as to fit the items. If you want to set the start and end date manually, for example to allow t...
Tue, 3 Mar, 2020 at 6:29 PM
How to disable linking in the gantt chart?
The dependency links are  derived from the work item links. This is controlled by Dependency Role widget parameter: If you do not want to let the user c...
Wed, 29 May, 2019 at 5:40 PM
How to configure the time scale?
You can use  Widget parameter Advanced > Scale ( D || W || M ) - it configures the scale of the timeline. The allowed values are: 'D' - day ...
Wed, 29 May, 2019 at 5:45 PM
How to disable rounding of task schedule based on scale
By default the the task's start and end dates is rounded to the nearest scale marks (days/weeks/or months). So if you set a scale to month, the sta...
Mon, 1 Jul, 2019 at 2:23 PM
How to change text on right?
So you want to render some more data  on the gantt? For example: Consider you have a Work item of type Epic and you want to render Owner field to the r...
Wed, 28 Aug, 2019 at 2:26 PM
How to show the difference of actual vs initial schedule.
Starting from version 1.5 the widget supports showing the actual vs initial schedule.  One time comparision You can compare the current schedule w...
Tue, 12 Oct, 2021 at 1:48 PM
How to set the parent schedule based on the children?
Sometimes you have type of work items, that you do not want to schedule explicitly, but you want the schedule to be derived from the children.  Starting ve...
Mon, 4 Jan, 2021 at 5:58 PM
How to render a milestone marker?
NOTE: Please update to version 1.6 before following this guidance. In this article we show you how to add milestone / release markers in the gantt chart...
Tue, 27 Aug, 2019 at 2:49 PM
Print Gantt Chart
Printing is tricky ... the Gantt is a scrollable component, so it is not as easy as just print-what-you-see. You can vote for the feature: https://feedb...
Fri, 8 Nov, 2019 at 3:24 PM
How to create a dependency link?
So you want to create dependencies between items on Gantt. This is simple with graphical link builder: Drag the start link circle Connect it with end ...
Mon, 17 Feb, 2020 at 11:59 AM