Yes, Gantt allows for a flexible “what-if” approach by letting you modify scenarios directly in the widget without committing those changes to Polarion. In Edit mode you can drag Items in the Gantt chart to see how shifting tasks affects timelines, dependencies, or effort - giving you instant visual feedback. As long as you don’t save the changes, they remain local.
Other option would be creating a separate Gantt charts using different data mappings or properties to reflect alternative scenarios.