It is good to know that there are different options for how to split the effort between assignees.
There are 2 possible ways how to count a task's effort if it has multiple assignees.
- By default, the effort is shown equally for all assignees. So for example, if a task has an initial estimate of 4 days in the resource view it will be shown as 4 days for all assignees.
- But in some cases, you may find it more useful to divide the effort equally between the assignees.
To do so, you should add this line to the Administration -> Configuration Properties:
nextedy.gantt.multiAssignmentSameEffortForAll=false
So now you know, that depending on your project needs you can use one of these options to show effort.
Check the description of these and other options for the default values and properties: click here
In case of issues, please send a message to: support@nextedy.com
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article